The volume calculation
Everything starts with cubic feet, then converts to yards or bags.
cubic yards = ft³ ÷ 27
A 10 × 10 ft slab at 4 inches: 10 × 10 × 0.333 = 33.33 ft³, which is 1.24 cubic yards. Add 10% for waste and you are buying for 36.67 ft³.
Bag yields
| Bag size | Yield | Bags per cubic yard |
|---|---|---|
| 80 lb | 0.60 ft³ | 45 |
| 60 lb | 0.45 ft³ | 60 |
| 40 lb | 0.30 ft³ | 90 |
Bag counts for common slabs
All at 4 inches thick, including a 10% waste allowance:
| Slab | Volume | Cubic yd | 80 lb bags | 60 lb bags |
|---|---|---|---|---|
| 4 × 4 ft | 5.3 ft³ | 0.20 | 10 | 14 |
| 8 × 10 ft | 26.7 ft³ | 0.99 | 49 | 66 |
| 10 × 10 ft | 33.3 ft³ | 1.24 | 62 | 82 |
| 12 × 12 ft | 48.0 ft³ | 1.78 | 88 | 118 |
| 20 × 20 ft | 133.3 ft³ | 4.94 | 245 | 326 |
Thickness changes everything
Volume scales directly with depth, so a modest thickness change is not modest at all:
Use 4 inches for patios, walkways and shed bases. Use 5 to 6 inches where vehicles park or heavy equipment sits.
The bags-versus-truck line
The practical threshold is about one cubic yard, or 45 bags of 80 lb mix. Above that, three problems compound:
- Cold joints. Hand-mixing 60+ bags takes long enough that early batches begin curing before later ones arrive, creating weak seams.
- Weight. 62 bags of 80 lb mix is nearly 5,000 lb to move by hand, twice — off the pallet and into the mixer.
- Cost. Bagged mix per cubic yard is typically well above ready-mix once you pass a yard or two, even allowing for short-load fees.
Before you pour
- Compact the sub-base. Four inches of compacted gravel under the slab prevents settlement cracking.
- Plan control joints. Cut them at roughly 24 to 36 times the slab thickness in feet — about every 8 to 10 feet for a 4-inch slab. Concrete will crack; joints decide where.
- Check the weather. Pouring below 40°F or above 90°F requires specific precautions or the cure suffers.
Working through a whole renovation? The same measure-first approach applies to paint, where the usual error is forgetting to subtract doors and windows.
Run your own numbers
FAQ
How many 80 lb bags of concrete make a cubic yard?
How many bags do I need for a 10×10 slab?
How thick should a concrete slab be?
Why add 10% for waste?
When should I order ready-mix instead of bags?
Sources
Primary references used for the figures and rules on this page.